Recent Projects
Koch Exploration
- Supplied 2 core rigs and 1 preset rig for a total of 211 rig days
- 24,683 man hours with 0 LTAs
- Drilled 37 core wells
- Drilled 18 preset wells
- Total of 12,021m drilled
- Total of 1,797m cored
- Fastest preset well was 0.79 days for 117.5m with 0.58 days from spud to rig release
- Fastest cored well was 2.0 days for 245m with 48m cored and 1.56 days from spud to rig release
“GroundForce was contracted to provide two core rigs and a preset rig that successfully preset 18 wells and drilled 37 core wells. Drilling to a total of 12,021m and cored 1,797m in 211 rig days they were able to complete their fastest preset well spud to rig release in 0.58 days for 117.5m. With 24,683 man hours and zero LTAs they were able to maintain greater than 96% core recovery throughout the winter project. We are looking forward to another successful winter project with GroundForce geoDrilling Solutions.”
Sunshine Oilsands
- Supplied cementing operations for preset rigs
- Innovative new idea that is compact, safe and efficient
- Dedicated cementing service with base operations including bulk cement silos saved rig time and lowered budgets for the winter project
- Eliminated wait times
- 68 preset cement jobs with no recorded incidents
“Groundforce supplied us with a dedicated cementing unit for our preset rigs and they came prepared for the winter project with their bulk cement silos and enough product to cover the winter. Their service eliminated wait times and saved rig time which lowered our budgets for the winter. With their innovative new cementing idea they were able to complete the 68 preset cement jobs in the project safely and efficiently with no recorded incidents.”
Laricina
- Supplied 1 core rig for a total of 48 rig days
- 9,939 man hours with 0 LTAs
- Drilled 9 core wells
- Total of 2954m drilled
- Total of 353m cored
“GroundForce operated one dedicated core rig for our winter project in which they drilled a total of nine successful strat wells with an average core recovery above 94% on the 353m cored of the 2954m drilled. GroundForce was able to complete the winter project without any LTAs in their 9,939 man hours.”